A 1,200-seat capability centre, opened on schedule
Full-floor procurement across five categories
Client
Global technology services firm
Location
Bengaluru, India
Year
2025
Category
Office Setup
Four floors of an under-construction tower had to be operational in fourteen weeks. The client had a design intent drawing and a headcount number. Everything between those two things was open.
Scope
- 01Specification against the architect's design intent
- 02Furniture, lighting, electrical, technology and consumables
- 03Floor-by-floor staged delivery to the construction programme
- 04Installation and snagging inside the handover window
The numbers behind it.
Customisation
Reception counter, wayfinding and all meeting room identification were produced to the architect's drawings and installed out of hours.
Result
Handover was achieved two days ahead of the committed date. The same specification has since been used for two further sites.
14
Weeks, brief to handover
5
Categories, one schedule
1,240
Seats delivered